TOGAF ADM Phase ==>
A: Initiation; B: Base Description; C: Target Architecture;
D: Opportunties and Solutions; E: Migration Planning;
F: Implementation; G: Architecture Maintenance

A

B

C

D

E

F

G

Not Covered
[*]

C4ISR Architecture
Framework reference

1.1  Overview and Summary Information (AV-1)

x

x

1.2  Integrated Dictionary (AV-2)

x[1]

1.3  High-Level Operational Concept Graphic (OV-1)

x

x

1.4  Operational Node Connectivity Description (OV-2)

x

x

1.5  Operational Information Exchange Matrix (OV-3)

x

1.6  System Interface Description (SV-1)

x

x

x

x

1.7  Technical Architecture Profile (TV-1)

x

x

x

2.1  Command Relationships Chart (OV-4)

x

2.2  Activity Model (Including Overlays) (OV-5)

x

2.3  Operational Activity Sequence and Timing Descriptions (OV-6a, 6b, 6c)

?

x

2.4  Logical Data Model (OV-7)

x

2.5  Systems Communications Description (SV-2)

x

2.6  Systems2 Matrix (SV-3)

x

2.7  Systems Functionality Description (SV-4)

?

x

2.8  Operational Activity to System Function Traceability Matrix (SV-5)

x

2.9  System Information Exchange Matrix (SV-6)

?

x

2.10  System Performance Parameters Matrix (SV-7)

x

2.11  System Evolution Description (SV-8)

 x

2.12  System Technology Forecasts (SV-9)

x

2.13  System Activity Sequence and Timing Descriptions  (SV-10a, 10b, 10c)

x

2.14  Physical Data Model (SV-11)

x

2.15   Standards Technology Forecast (TV-2)

 x

[*] These products are not covered in the TOGAF ADM because the ADM does not go down to the level of detail that these particular products of the C4ISR Architecture Framework address. TOGAF currently positions these C4ISR products at the level of system design rather than architecture. Specific organizations tailoring the ADM to their own needs might decide to go this level of detail, however (typically, by including them in Phase C, Target Architecture). 

[1]  This could be the Building Blocks Information Base